Ganttview task are not in line 2 years 4 weeks ago #22441

  • Knut
  • Knut 's Avatar
  • OFFLINE
  • Senior Boarder
  • Posts: 46
  • Karma: 0
How to fix so that the task name and date bars is flush?
after 5 task they start to miss match.
And after 10 line the taske are one line wrong.

ganttview1.jpg
Last Edit: 2 years 4 weeks ago by Knut .
The administrator has disabled public write access.

Re: Ganttview task are not in line 2 years 4 weeks ago #22455

  • eldy
  • eldy's Avatar
  • OFFLINE
  • Administrateur
  • Posts: 1424
  • Thank you received: 14
  • Karma: 155
Do you have problem if you use the skin "eldy" ?
Laurent Destailleur (alias eldy, Dolibarr grade: Yoda).
- Dolibarr in the Cloud: DoliCloud, the OpenSource hosting solution for your Dolibar ERP & CRM.
- Android app for Dolibarr: DoliDroid
- Teclib.com, your Open source solution
The administrator has disabled public write access.

Re: Ganttview task are not in line 2 years 3 weeks ago #22458

  • Knut
  • Knut 's Avatar
  • OFFLINE
  • Senior Boarder
  • Posts: 46
  • Karma: 0
I have trouble getting the left to be in line with the right side of the table.
And it's the same if I switch skins.
gantt.jpg
Last Edit: 2 years 3 weeks ago by Knut .