Where is "Hourly rates" set on a project?

v23

Added a Time task to a project, and according to Doli the hourly rate for these tasks is 250/h. I just created the project but have not entered anything about costs and I cannot find where to alter it.

Where can I change the hourly rate?

Hi @gurksallad

I think you will have to set this here on the user card page.

Thanks & Regards
Saikat Koley
Software Developer(Dolibarr)
Call/WhatsApp : +919903256573
Email : saikatkoley@hotmail.com
https://www.linkedin.com/in/saikatkoley/

1 Like

Thank you, that was it.

1 Like